Retaining wall block calculator
Blocks = courses × blocks in a course: a 20 ft wall 2 ft high in 12 × 4 in blocks, with one course buried, is 7 courses of 20 blocks, or 147 blocks with 5% extra, on 0.74 cubic yards of base rock.
Example: replace these measurements
Your wall list
147 retaining wall blocks
147 retaining wall blocks
40 sq ft measured
Your shopping list
- 147 retaining wall blocks
Quantities and package details
- Courses
- 7, 1 of them below the ground
- Blocks in each course
- 20
- Blocks before extra
- 140
- Buried depth
- 4 in (1 in a foot of wall height, a whole course)
- Caps
- Enter the cap length if the wall has caps
- Base rock, compacted
- 0.74 cu yd (a 24 in wide trench, 6 in deep)
- Drainage rock behind the wall
- 1.73 cu yd (12 in deep, the full 28 in height), plus the cores of hollow blocks
- Drain pipe
- 20 ft along the base if the site drains poorly
The calculation
- Courses: (24 in of wall + 4 in buried) ÷ 4 in, rounded up = 7
- Each course: 240 in ÷ 12 in, rounded up = 20 blocks
- 7 × 20 = 140 blocks; with 5% extra, rounded up = 147
- Base rock: 24 × 6 × 240 in ÷ 46,656 = 0.74 cu yd
- Drainage rock: 12 × 28 × 240 in ÷ 46,656 = 1.73 cu yd
Common questions
How many retaining wall blocks do I need?
Divide the wall length by the block face length for the blocks in a course, and the wall height plus the buried depth by the block height for the courses, rounding both up. A 20 ft wall 2 ft high in 12 × 4 in blocks, with one course buried, is 20 blocks a course and 7 courses: 140 blocks, 147 with 5% extra.
How deep should the first course be buried?
Allan Block buries 1 in for every foot of wall height, on top of at least 6 in of compacted crushed rock in the trench. In whole courses that is usually one course for a garden wall and two for a wall over 4 ft.
How much gravel goes behind a retaining wall?
Allan Block fills 12 in behind the blocks with crushed rock the full height of the wall, and the cores of hollow blocks too. Behind a 20 ft wall 28 in tall that is about 1.7 cubic yards, plus 0.74 cubic yards for a 24 × 6 in base.
When does a retaining wall need an engineer?
Under the International Residential Code (R404.4), a wall that holds back more than 48 in of soil needs a design, and so does one over 24 in high with a driveway, a building or another load above it. A slope above the wall adds to the load too. Your building department decides, so ask before you buy.
How to plan the quantity
Courses = the wall height plus the buried depth, divided by the block height and rounded up. Blocks in each course = the wall length divided by the block face length, rounded up. The buried course sits below ground so the wall cannot slide out at its foot.
The base is a trench of compacted crushed rock under the first course. Behind the blocks, a band of the same rock the full height of the wall lets water drain instead of pushing on the wall; hollow blocks are filled with it too.
Allan Block puts a drain pipe at the back of the base for any reinforced wall, for walls over 4 ft and on sites with poor drainage; it must run out to daylight.
Before you order
- A wall that holds back more than 48 in of soil (the difference between the ground in front of it and behind it) needs a design under the International Residential Code (R404.4), and so does one over 24 in high with a driveway, a building or another load above it. A slope above the wall adds to the load too. Check with your local building department.
- This counts a straight wall on level ground. Steps in the base, curves, corners, stairs and geogrid reinforcement change the count: follow the block maker’s guide for them.